Fehmarnbelt Fixed LinkTunnel construction - delays and cost explosion

Christian Tiedt

 · 04.10.2025

Fehmarnbelt Fixed Link: Tunnel construction - delays and cost explosionPhoto: DB Netz/Rambøll
Visualisation of the north portal of the Fehmarnsund Tunnel on the island of Fehmarn. The bridge is to be retained for cycle and pedestrian traffic.
The construction work and restricted areas in the area of the Fehmarnbelt crossing could be with skippers in the north for much longer. There are delays at the Fehmarnbelt and Fehmarn Sound - and an explosion in costs.

According to regional media reports, both the Fehmarnbelt tunnel between the Danish island of Lolland and the German island of Fehmarn, which is already under construction, and the planned much shorter tunnel connecting Fehmarn with the Schleswig-Holstein mainland are affected by delays. The Fehmarnbelt tunnel will replace the existing ageing bridge, which has already become a bottleneck for traffic.

Commodity prices to blame for cost explosion

According to information from NDR, the costs for the 1.8 kilometre long tunnel under the Fehmarnsund now calculated at 2.3 billion euros. The original estimate was 714 million euros. The tripling of the sum is due to increased raw material prices, among other things.

The Fehmarnsund Tunnel is to accommodate four lanes for road traffic and two tracks for rail traffic. According to the Federal Railway Authority, completion is now only expected after three to four years of construction. The tunnel, together with the Fehmarnbelt Tunnel, was originally scheduled to open in 2029.

Special ship still waiting for approval

However, the actual core project of the Fehmarnbelt link itself, the 18 kilometre long Fehmarnbelt tunnelThe reason given by Femern, the Danish project company commissioned with planning and construction, which in turn is part of the Danish state holding company Sund & Bælt, is problems with the specialised ship "Ivy".

The 100 metre long vehicle for lowering the tunnel elements was specially developed for the construction of the Fehmarnbelt Tunnel, but has not yet been fully tested and approved by the authorities. At present, the project is already 18 months behind the original schedule.

How do you like this article?

German requirements for Fehmarnbelt link

However, it is questionable whether the lost time can still be made up for. At the time the contract was signed, the German side had not yet received final authorisation. Some of the requirements on the German side, for example with regard to the underwater noise of the working vessels, only came into effect later.

"The contracts are almost ten years old and were concluded before the coronavirus pandemic or the war in Ukraine broke out. And we didn't know the full extent of the German authorities' requirements at the time," says Mikkel Hemmingsen, CEO of Sund & Bælt.

With a length of 18 kilometres, the Fehmarnbelt tunnel will be the longest immersed tunnel in the world, even if the date of completion is still unclear. However, at least the expansion of the railway connection on the Danish side to the capital Copenhagen is on schedule.

Christian Tiedt

Christian Tiedt

Editor Travel

Christian Tiedt was born in Hamburg in 1975, but grew up in the northern suburbs of the city - except for numerous visits to the harbor, North Sea and Baltic Sea, but without direct access to water sports for a long time. His first adventures then took place on dry land: With the classics from Chichester, Slocum and Co. After completing his vocational training, his studies finally gave him the opportunity (in terms of time) to get active on the water - and to obtain the relevant licenses. First with cruising and then, when he joined BOOTE in 2004, with motorboats of all kinds. In the meantime, Christian has been able to get to know almost all of Europe (and some more distant destinations) on his own keel and prefers to share his adventures and experiences as head of the travel department for YACHT and BOOTE in cruise reports.

Most read in category Travel